We are proposing to increase the size of Phase 2 of the regeneration of Wornington Green Estate to allow more people to move into their new homes more quickly and provide more of the park space earlier.

The revised phasing plan shows the current five phases and the proposed change to three phases together with the likely timetable.

You will have already received a letter explaining what this means to you and your household. The block by block table which was included with the letter is shown again here for information.

If you want to comment on the proposed changes please do so by contacting Sue Hannah by Friday 7 December.

If you would like to make an appointment to discuss the regeneration or your current housing situation please contact your Housing and Regeneration Co-ordinator, Liza, Mary or Mushtaq – refer to Contact Us page.

Previously Published Phasing Plan
(taking into account delays to Phase 1)

Phase 1
January 2012 – May 2015
(50% of park available)
Phase 2
March 2015 – July 2016
(50% of park available)
Phase 3
September 2016 – April 2021
(50% of park available)
Phase 4
April 2019 – June 2022
(89% of park available on completion)
Phase 5
September 2021 – April 2023
(100% of park available on completion)

Revised Phasing Plan

Phase 1
January 2012 – May 2015
(50% of park available)
Phase 2
November 2014 – November 2017 (80% of park available on completion – retained Venture Centre shaded blue)
Phase 3
August 2017 – March 2021 (100% of park available on completion)